New Housing Information

Evergreen plans to replace its four current first year residence halls (A–D) with new first year housing to open in September 2019.

new housing rendering

See the Latest Images

Timeline

  • February 2017 - September 2017: Design Phase
  • September 2017 - March 2018: Permits, Blueprints, Documents, and Bidding Phase
  • April 2018 - July 2019: Construction Phase
  • September 2019: New Students Move in

2015-16 Decisions Made

  • Current first year halls needed to be replaced, it is cost prohibitive and structurally difficult to renovate them.
  • New first year housing will be traditional hallways with single/double rooms and shared restrooms- no suites.
  • New first year housing will have wide hallways and more open spaces than current buildings.
  • The total budget for the new first year halls is approximately $40 million, primarily paid for with bonds and RAD funds, not state funds.
  • Board of Trustees approved the first phase of building in July 2016. (Replacing buildings A-D, to create new first year housing to open fall 2019.)
  • Increase first year residence halls occupancy from current buildings A-D capacity of 450 to 480 residents in new building(s).

More Information and Updates