Project # 319111
Description:With this project, the damaged roadway will be repaired, motorized and non-motorized traffic safety will be increased, and signage will be improved. The design includes one round about at McCann Plaza, intersection improvement at Overhulse, the roadway will be reduced to one lane in each direction and bike and walk paths will be added to both sides of the Parkway. The contract has been awarded for this project, see below for contact information. Construction on this project will be from mid-April through mid July 2005. Contact the project manager for more information. Construction Updates and Progress ReportsProject Budget:$1,035,360.40 Project Management: The Evergreen State College Architect: Parametrix Contractor: Roglin's Inc. |