Demolition continues. Interior walls and flooring have been removed. Windows have begun to be removed. Asbestos abatement is almost complete.
Outside:
The new outside ADA ramp to Red Square is being framed and the concrete formation of the first floor entryway has begun.
![]() |
![]() |
![]() |
![]() |
|---|---|---|---|