The interior of the first and second floors is being demolished. Asbestos has been removed from the second and third floor with removal to begin on the first floor. The concrete seismic walls are being constructed throughout the middle of the building.

Outside:

New windows and exterior walls are being cut and cored. Holes are being dug for the new foundation.